Minera Alamos Advances Construction of Its Santana Gold Project, Mexico

Published: February 1, 2021 |

[Click image to enlarge]

Minera Alamos released a construction update detailing progress at the Santana gold project, Sonora, Mexico, as the company advances towards the commencement of mining.

“We have made tremendous progress towards the completion of construction at the Santana gold project since activities were allowed to restart around the middle of last year following the widespread Covid-19 shutdowns. Major civil works are now drawing to an end and the focus has shifted towards the final placement of field connections required for fluid handling systems involved in the leach process. The overall project site is quickly taking shape with the plant, remaining buildings and storage facilities all beginning their final construction and installation phases over the coming month.  In parallel, our mining group continues to finalize start-up optimization plans for the Nicho and Nicho Norte open pits.” said Darren Koningen, CEO of Minera Alamos.

“We would like to take this opportunity to thank our contractors and team in Mexico for the excellent progress in building the Santana operation at a time where so many logistical challenges presented themselves. As construction activities draw to a close at Santana the project’s development is a testament to their hard work and commitment,” added Koningen.

• Leach solution ponds (barren and pregnant) are now fully lined and ready for operations.
 
• The plant foundations have been completed and all previously fabricated plant structures (including carbon columns for gold recovery) have been delivered to site in preparation for final installation that is now underway.
 
• The majority of the civil works for the heap leach pad area have been completed and the installation of the pad liner has commenced this week.
 
• Foundations for additional site infrastructure items including the warehouse and fuel storage areas are also complete.
 
• The crushing system previously acquired for potential future expansions at Santana or at the Company’s Cerro de Oro project is in transit from the U.S. to the company’s staging facilities in Obregon, Sonora
 
• The company is well funded to complete construction of Santana while advancing development activities across its pipeline of projects.

Lined Solution Ponds
With the vast amount of construction activity in 2020 revolving around earthworks for the plant, ponds and pad the final installation of liners and plant process equipment is moving forward quite rapidly as can be seen in the transition from unlined to fully lined ponds in just a few weeks. The main pad liner is expected to be installed over the coming weeks in parallel with the final installation and connection of equipment related to the gold recovery plant.

Crushing System
In 2020 the company was able to acquire a complete crushing, screen and agglomeration system suitable for gold heap leach operations including the associated material handling systems and power generation infrastructure. The system is currently being transported from the U.S. where it had been stored to the company’s existing storage facilities in Obregon, Sonora. Internal planning studies are underway to finalize decisions as to which items will be designated for future use at the Santana operation versus the company’s recently acquired Cerro De Oro gold project in Zacatecas.


About Minera Alamos
Minera Alamos is a gold development company poised to join the ranks of gold producers in 2021. The company has a portfolio of high-quality Mexican assets, including the 100 percent owned Santana open-pit, heap-leach development project in Sonora that is currently under construction, and which is expected to have its first gold production in early 2021.  The newly acquired 100 percent owned Cerro de Oro oxide gold project in northern Zacatecas. The 100 percent owned La Fortuna open pit gold project in Durango. A construction decision on La Fortuna could be made in late 2020 or early 2021, highlighting the organic growth the existing project portfolio can provide to the overall production profile.  Minera Alamos is built around its operating team that together brought 3 mines into production in Mexico over the last 13 years.

To stop by Minera Alamos’ website, CLICK HERE


Be in-the-know when you’re on-the-go!

FREE eNews delivery service to your email twice-weekly. With a focus on lead-driven news, our news service will help you develop new business contacts on an on-going basis.

CLICK HERE to register your email address.


Copyright © 2020 Mining Connection LLC. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed without permission.

For licensing permission, .(JavaScript must be enabled to view this email address)

Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




Advertisement