First Cobalt Releases Positive Feasibility Study Results for Canadian Cobalt Refinery Expansion
First Cobalt released positive results from an independent feasibility study conducted on its permitted cobalt refinery in Ontario, Canada. The study contemplates expanding the existing facility and adapting it to be North America’s first producer of cobalt sulfate, an essential component in the manufacturing of batteries for electric vehicles.
The feasibility study demonstrates that the First Cobalt Refinery project can become a viable, globally competitive player in the North American and European electric vehicle (EV) supply chain. The study reinforces the strength of First Cobalt’s business strategy for a rapidly evolving EV market that is heavily dependent on supply from China.
“This is an important milestone in our efforts to disrupt the existing cobalt supply chain. The study shows strong asset-level economics that position the refinery to be competitive globally and provide attractive investment returns. The outlook for electric vehicles and the push by automakers to develop shorter supply chains creates an excellent opportunity,” said Trent Mell, First Cobalt president and CEO.
With most of the world’s cobalt refining capacity located in China, there is strong demand for a North American alternative. Our focus will now turn to working with Glencore, our strategic partner, on implementing a new, ethical and transparent supply chain,” added Mell.
“I would like to congratulate the First Cobalt team on a positive feasibility study. As the world transitions to a low-carbon economy, cobalt will play an essential role in the growth of mobility electrification. We look forward to working with First Cobalt to bring a sustainable source of cobalt to the North American market,” said Nico Paraskevas, Glencore’s head of copper and cobalt marketing.
PROJECT OVERVIEW
The First Cobalt Refinery is a hydrometallurgical cobalt refinery located north of Toronto, Canada. The facility was permitted in 1996 with a nominal throughput of 12 tonnes per day (tpd) and operated intermittently until 2015, producing a cobalt carbonate product along with nickel carbonate and silver precipitate. The facility is located on 120 acres, with two settling ponds and an autoclave pond. The current footprint also includes a large warehouse building that once housed a conventional mill.
Testing of third-party cobalt hydroxide in 2019 using the refinery flow sheet confirmed suitability of cobalt hydroxide as a source of feed to produce a high purity, battery grade cobalt sulfate.
In July 2019, First Cobalt and Glencore agreed to a partnership framework providing for a non-dilutive, fully funded, phased approach to recommission the refinery. Subject to certain conditions, including the completion of a positive feasibility study and agreement upon commercial terms, the framework agreement contemplates that First Cobalt will treat cobalt feed material supplied from Glencore’s DRC operations for an initial term of up to 4½ years on a tolling basis, with Glencore providing up to 100 percent of the capital required to recommission and expand the facility. The objective is to produce approximately 25,000 tonnes of cobalt sulfate per annum for the electric vehicle market.
Ausenco Engineering Canada Inc. completed two studies in support of this strategic partnership: (1) a prefeasibility study on an interim recommissioning of the refinery by late 2020 or early 2021 using exiting permits and equipment to qualify a cobalt sulfate product with end-users, and (2) a feasibility study on an expansion scenario to 55 tpd nameplate capacity, targeted for commissioning in Q4 2021. The strategic objective of the partners is to achieve 5,000 tonnes per annum of cobalt production (55 tpd nameplate, 50 tpd average), which would account for approximately 5 percent of the current global refined cobalt market and an even larger share of the cobalt sulfate chemical market.
In conjunction with the feasibility study, discussions have been ongoing with potential automotive offtake partners as well as several lenders interested in providing a portion of the capital cost along with Glencore.
COBALT MARKET
According to a report commissioned from Benchmark Mineral Intelligence, there are currently no plans to commission new cobalt refineries outside of China other than First Cobalt. They also note that most automotive companies outside of China are interested in sourcing cobalt sulfate closer to their manufacturing facilities or from suppliers located outside of China.
REFINERY DESIGN DETAILS
The First Cobalt Refinery sits on a 40-acre land package and includes the refinery building complex, one tailings pond and two water treatment ponds. The main refinery gallery in the building complex houses the pressure oxidation circuit, solvent extraction circuit (SX), product filtration and a control room. The main building also includes a laboratory, administrative offices and changerooms. Other structures attached to the main gallery include a warehouse which previously housed a conventional milling circuit, a Merrill-Crowe building, a mechanical shop and a High-Density Sludge (HDS) building. There is also an external tank farm located along the north side of the complex. The feasibility study criteria were to make the best use of existing infrastructure while keeping as much as possible within the current footprint.
The proposed new layout adds two new simple engineered structures to the main complex; one for tailings belt filters and the other for crystallization and product bagging. A new external building is also contemplated to house an expanded SX circuit and sodium management infrastructure. Other changes to the site layout include additional tankage for reagent storage in the tank farm area and improvements to the ring-road around the refinery to accommodate transport trucks (Appendix 2).
An 80-acre property located to the north is owned by First Cobalt and it will be the location of a new dry stacked tailings management facility. Tailings from the process are a gypsum that can be readily dewatered and stacked for permanent dry storage. First Cobalt has the advantage that the field to the north is underlain by more than 6 metres of clay, some of which will be excavated to increase storage capacity, with the excavated clay being reused to construct the new tailings storage facility and permanently rehabilitate the Autoclave pond and the new tailings facility at end of Project. Only half of the field to the north is planned for the new tailings management facility, which will have approximately 17 years of storage capacity. The other half of the field remains available to be developed as additional storage for an additional 17 years of operation. The existing Upper Pond will be expanded to collect surface water from freshet and summer storm events for safe return to the environment.
Retrofitting of the existing buildings and equipment, new construction and installation of new equipment is expected to take approximately 12 months.
Cobalt hydroxide feed is expected to arrive at the Port of Montreal via ocean freight where it will be transferred onto rail cars to be delivered to a siding on the Ontario Northland railway in Cobalt, Ontario. The Ontario Northland rail line passes 2 km west of the refinery Road. Hydroxide feed will be trucked from the rail siding to the refinery and refined cobalt sulfate product will be backhauled to the siding for reloading onto rail cars for shipment to end markets.
PROCESS AND METALLURGY
Cobalt hydroxide feed material will arrive in bulk bags and be unloaded into the refinery warehouse. The bulk bags will be lifted with the refinery’s overhead crane, where the bags will be emptied into a re-pulping system. The slurry is then pumped to a leach circuit where it is leached with sulphuric acid under atmospheric conditions.
Slurry exiting the leach tanks is pumped to the neutralization circuit where limestone is added in order to raise the pH and precipitate impurities such as iron. To minimize downstream scaling, the slurry is cooled to 30-35°C in a cooling tower which reduces soluble gypsum content. The precipitated solids are removed through thickening and filtration.
Prior to solvent extraction (SX), the solution is re-heated to raise gypsum solubility and prevent subsequent precipitation in the mixer settlers. The first SX circuit is Impurity SX (ISX), targeting the removal of impurities such as manganese, copper, zinc, calcium, and iron. The extraction raffinate after this step primarily contains cobalt, with nickel and magnesium present as impurities. The strip liquor reports to effluent treatment, where the impurities are precipitated and removed from solution prior to discharge.
The second SX circuit is Cobalt SX (CoSX) which loads cobalt onto the organic solvent while any residual impurities remain in the aqueous phase. The cobalt-loaded organic then proceeds to the scrubbing mixer-settlers where the pH is adjusted to remove impurities such as magnesium and nickel that were loaded in the extraction stage. The scrubbed organic goes to a final stripping stage where the pH is lowered to bring the cobalt out of the organic phase and into the aqueous strip liquor stream. Once filtered to remove entrained organic, the strip liquor enters the crystallization step.
The filtered strip liquor is pumped to a mechanical vapor re-compression forced circulation crystallizer. The crystallizer functions by evaporating water using steam in a heat exchanger, supersaturating the cobalt-rich strip liquor and causing crystallization to occur. The bleed stream of cobalt sulphate crystals reports to a thickener and centrifuge for dewatering. Together they separate the solid and liquid components of the slurry, producing a dewatered product at less than 3 percent free moisture. The centrifuged crystals then report to a fluid bed dryer to reduce the moisture content of the crystals to below 0.2 percent w/w. Once dried, the final product is bagged and is ready for onward shipment to the end customer.
TAILINGS STORAGE FACILITY
Knight Piésold Ltd. completed geotechnical drilling on the potential dry stack tailings area in First Cobalt’s 80-acre clay field to the north of the refinery complex to support feasibility-level design work. Dry stack or filtered tailings have several benefits, including a smaller environmental footprint and lower water treatment requirements.
The current design contemplated using approximately half of the field, providing capacity for 17 years of production at 50 tpd (55 tpd nameplate). Thereafter, it is envisioned that the other half of the field could be used for an additional 17 years of dry tailings storage. It is believed that additional land would be readily available for future expansions. For the purpose of assessing project economics, Ausenco has assumed an 11-year project life.
WATER MANAGEMENT
Process water from the refinery will be treated to a level that meets or exceeds regulatory requirements before being returned to the environment. Environmental testing and design by First Cobalt’s consultants have devised a treatment process to ensure that the return of process water to the environment is done in a compliant and environmentally friendly manner. Broadly speaking, there are two main criteria that must be met before water can be discharged. First, metals and other elements as prescribed cannot exceed predetermined thresholds. Second, the water being discharged should not be acutely toxic to aquatic life.
Owing to the use of sodium hydroxide in the process flowsheet that has been designed, effluent from the refining process would have an elevated concentration of sodium. There are no federal or provincial discharge limits nor surface water quality objectives or guidelines for sodium. However, it was determined that the amount of sodium in the effluent could be toxic to aquatic life. In order to satisfy the requirements of a feasibility level study, the study contemplates installing an established technological solution of evaporation and crystallization to remove sodium content.
The evaporation and crystallization technology is proven to be effective for removing sodium from the effluent but it is more expensive than other alternatives. In this process, the effluent stream is first concentrated by evaporation to reduce the volume reporting to the crystallizer. The resulting brine is then fed to a sodium crystallizer in which a crystalline sodium sulfate product is formed. This crystalline product is sent for offsite disposal.
First Cobalt identified a number of other solutions for managing the sodium that could significantly reduce capital and operating costs, including substituting sodium-based reagents for alternatives not containing sodium, making process changes or implementing other management solutions to reduce the sodium concentration in the effluent. Due to time constraints, Ausenco recommended that the study incorporate a well-established treatment process and that alternatives be more fully assessed over the next few months.
PERMITTING
Regarding the ability of First Cobalt to legally operate the refinery under the current regulatory regime in Ontario, three environmental approvals and a closure plan amendment are required. The Air Environmental Compliance Approval (Air ECA) and Industrial Sewage Works ECA have been submitted, approved, and amended from time-to-time by previous owners of the refinery and remain in good standing. The Permit to Take Water (PTTW) is the third environmental approval and requires renewal from time-to-time. As the refinery has not operated since mid-2015, the current PTTW has expired. First Cobalt and Story Environmental prepared a new PTTW application, consulted with local Indigenous Communities and subsequently submitted the PTTW application in March 2020. Under normal circumstances, First Cobalt’s consultants have advised that the new PTTW might be expected within 6 months of submission.
The refinery has a Closure Plan on file with the Ontario Ministry of Energy, Northern Development and Mines (ENDM). In October 2019, the company was granted a transfer of the Closure Plan from the previous owner to Cobalt Camp Refinery Ltd., a wholly owned subsidiary of First Cobalt. In conjunction with the transfer, First Cobalt also increased the amount of Financial Assurance held as cash by ENDM.
With the exception of the PTTW which the company expects to receive in due course, the refinery has all the necessary approvals in place to restart production at its permitted feed rate of up to 12 tpd.
For the expansion scenario envisioned by this feasibility study, the Air ECA, Industrial Sewage Works ECA and the Closure Plan will all require amendment to reflect the new operating and environmental regimes. Work has already begun collecting baseline and other data in support of these ECA amendments. First Cobalt currently expects to be able to make the application for these ECA amendments before the end of 2020. Based on the feasibility work conducted to date, no hurdles have been identified which would compromise the approval of these applications. Indigenous Community and public consultation will be continuing throughout the ongoing scoping studies and the approval process.
To read more details in the company’s press release, CLICK HERE
About First Cobalt
First Cobalt owns North America’s only permitted cobalt refinery. Cobalt refining is a critical component in the manufacturing of batteries for electric vehicles, consumer electronics and industrial applications. Cobalt is a critical mineral and forms a foundational piece of the next generation of the North American auto sector. First Cobalt also owns an advanced cobalt project in the United States and controls significant mineral assets in the Canadian Cobalt Camp.
To stop by First Cobalt’s website, CLICK HERE
Be in-the-know when you’re on-the-go!
FREE eNews delivery service to your email twice-weekly. With a focus on lead-driven news, our news service will help you develop new business contacts on an on-going basis.
CLICK HERE to register your email address.
Copyright © 2020 Mining Connection LLC. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed without permission.
For licensing permission, .(JavaScript must be enabled to view this email address)