EPA Recommends Against Reissuing Permit for PolyMet Mine, Minnesota

Published: May 4, 2022 |

[Click image to enlarge]

Federal regulators recommended Tuesday that the Army Corps of Engineers decline to reissue a key permit for the proposed PolyMet copper-nickel mine, saying the project could raise levels of mercury and other pollutants downstream from the site in northeastern Minnesota.

It’s just a recommendation, but it could deal a severe blow to the $1 billion mine if the Army Corps accepts the advice from the U.S. Environmental Protection Agency, Minnesota Public Radio reported.

The EPA announced its position at the start of a three-day hearing in Carlton, where the Corps is taking testimony on whether PolyMet would violate the water quality standards of the Fond du Lac Band of Lake Superior Chippewa, whose reservation lies down the St. Louis River from the site.

The Corps is considering whether to reinstate the project’s wetlands permit, one of several key approvals PolyMet needs to begin construction. It’s one of three critical PolyMet permits that have been suspended as the project remains tied up in court and regulatory proceedings.

The EPA determined that there were no conditions that the Corps could place on the wetlands permit that would ensure compliance with the tribe’s water quality regulations, which are stricter than the state’s. Tribal members rely on fish from the St. Louis River, which flows through the reservation, but consumption advisories limit the number of fish that can be safely eaten from it.

Environmental groups that oppose PolyMet said they expect the EPA’s position to carry significant weight with the Corps when it decides whether to reinstate or revoke the wetlands permit, and that if the Corps doesn’t follow the EPA’s advice, a court would likely reject the Corps’ decision.

But PolyMet said in a statement that the agency “disregarded the science-based conclusions” reached in the project’s environmental review and permitting process. The company said it’s confident the Corps will affirm the permit after it considers all the evidence.

PolyMet contends the project will actually reduce mercury and sulfate discharges into the St. Louis River watershed because it will clean up an old iron mining waste pond at the processing plant site. The company pointed out that the site is more than 100 river miles upstream from the reservation.

The permit in question would allow PolyMet to fill around 1,000 acres of wetlands at its proposed mine site. The Corps approved the permit in 2019, but a federal judge ruled last year that the government failed to notify the downstream tribe about the potential impacts. So the Corps suspended the permit, leading to the current hearing.

Source: Associated Press


About PolyMet
PolyMet is a mine development company that owns 100 percent of the NorthMet Project, the first large-scale project to be permitted within the Duluth Complex in northeastern Minnesota, one of the world’s major, undeveloped mining regions. NorthMet has significant proven and probable reserves of copper, nickel and palladium – metals vital to global carbon reduction efforts – in addition to marketable reserves of cobalt, platinum and gold. When operational, NorthMet will become one of the leading producers of nickel, palladium and cobalt in the U.S., providing a much needed, responsibly mined source of these critical and essential metals.

To stop by PolyMet’s website, CLICK HERE


Be in-the-know when you’re on-the-go!

FREE eNews delivery service to your email twice-weekly. With a focus on lead-driven news, our news service will help you develop new business contacts on an on-going basis.

CLICK HERE to register your email address.

Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




Advertisement