Pure Energy Minerals Completes Successful Lithium Brine Pumping Test at Clayton Valley South Project
Pure Energy Minerals Limited has completed a constant-rate pumping test at its newest exploration well, CV-8, at the Clayton Valley South Project (CVS Project). The test ran continuously for three days and included a collection of brine samples along with extensive hydrogeological data on the brine aquifer system. CV-8 is believed to be the deepest well drilled in Clayton Valley, having reached a total depth of 3,194 ft (974 m) below ground level. The drillers completed the well with casing and filter pack to a depth of 2,874 ft (876 m), installing perforated casing and seals around two separate intervals. This type of well construction allows for isolation and separate testing of shallow and deeper zones of the aquifer system.
“CV-8 probed greater depths and encountered new aquifers not yet seen on the CVS Project. It is significant that CV-8 more than doubled the thickness of known brine-saturated sediments in our resource when compared with the drilling in the maiden resource,” said Patrick Highsmith, Pure Energy Minerals CEO.
“This pumping test is an important milestone as it adds considerably to our knowledge for the resource model and the preliminary design of a production well field. We look forward to working through the data as we update the mineral resource and deliver the first PEA at the CVS Project,” added Patrick Highsmith.
The well encountered numerous aquifers, including the interlayered volcanic ash and silt that are typical of Clayton Valley lithium production. At greater depths, the well passed through travertine (hot springs deposits) and conglomerate (gravel) that had not previously been described on the CVS Project, thus offering the potential for new brine hosting aquifers. Down hole fluid logging revealed elevated electrical conductivity to the bottom of the well, suggesting the presence of brine at greater depths than any previous sampling on the project.
The pumping test was configured using an electric submersible pump and monitoring apparatus in CV-8. The test ran at a constant pumping rate of approximately 2.0 litres per second (30 gallons per minute) for its duration. The hydrogeologists collected approximately 48 separate brine samples (including QA/QC samples) for lithium analysis over the 72-hour pumping period.
Monitoring during the test revealed that the extracted brine from CV-8 reached near steady-state elevated fluid conductivity and fluid density, comparable to other brine wells on the CVS Project. Based on previously observed correlations between conductivity and lithium content, this suggests the production of consistent lithium-bearing brine during the entire pumping test. Data collected during the pumping test will be used to enhance understanding of the hydrogeology of the CVS Project. The team also collected depth-specific brine samples for chemical analysis. These results are expected in April. The upcoming preliminary economic assessment (PEA) will include a full discussion and interpretation of the data from CV-8.
This pumping test was designed and supervised by Pure Energy’s hydrogeological consulting specialists, Montgomery & Associates. The test was performed in accordance with State of Nevada waivers and permits issued to Pure Energy by the Nevada Division of Water Resources and the Division of Environmental Protection, which allowed for the extraction of brine from the well for the extended duration of this test and subsequent discharge to surface.
About Pure Energy Minerals Ltd.
Pure Energy is a lithium resource developer that is driven to become a low-cost supplier for the burgeoning lithium battery industry. The company is currently focused on the development of the CVS Lithium Brine Project and the adjoining Glory Lithium Clay Project in Clayton Valley, Nevada. Pure Energy also recently announced the acquisition of a purchase option on a major new lithium brine project in the Lithium Triangle of South America, the Terra Cotta Project (TCP). The TCP is located on Pocitos Salar in Salta, Argentina, where it enjoys some of the best infrastructure and access of any lithium brine exploration project in the country. Execution of the definitive agreement concerning the Terra Cotta purchase option is expected during Q1 of 2017.
Pure Energy has developed core strengths in innovative development and processing technologies for lithium brines and lithium mineral deposits.
To stop by Pure Energy Minerals’ website, CLICK HERE
Be in-the-know when you’re on-the-go!
FREE eNews delivery service to your email twice-weekly. With a focus on lead-driven news, our news service will help you develop new business contacts on an on-going basis.
CLICK HERE to register your email address.
Copyright © 2017 Mining Connection LLC. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed without permission.
For licensing permission, .(JavaScript must be enabled to view this email address)