Longwall Mining
Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




PolyMet Submits Permit to Mine Application to Minnesota DNR

Published: November 8, 2016 |

[Click image to enlarge]

PolyMet Mining Corp. has submitted its permit to mine application to the Minnesota Department of Natural Resources (DNR).

The permit to mine is one of several major permits required to construct and operate the NorthMet copper-nickel-precious metals project located in northeastern Minnesota. The application is the last of the major permit applications, following submission of water-related and air quality permit applications to the Minnesota Pollution Control Agency (PCA) and DNR during the summer.

The more than 15,000-page permit to mine application details the methods and controls PolyMet proposes to use to mine and process ore in an environmentally responsible and safe manner, plans to mitigate environmental impacts, and financial assurance to cover the costs of reclamation, closure and post-closure in compliance with state law.

“This application is the product of more than a decade of independent and peer-reviewed scientific studies and analysis. It reflects the culmination of thousands of hours of meticulous work by the PolyMet team and our consultants and advisors,” said Jon Cherry, president and CEO of PolyMet.

“It demonstrates in detail the numerous steps we would take to ensure the mine operates in an environmentally responsible and safe manner, meets the high standards and expectations we and others have set for the project, and that there will be funds set aside to ensure that taxpayer dollars will not be needed for reclamation,” added Cherry.

In conjunction with the air- and water-related permit applications that were submitted during the summer, the Permit to Mine application provides details of various aspects of the construction, mining, processing, and ultimate closure.

The NorthMet Project is estimated to require approximately two million hours of construction labor and would create approximately 360 long-term jobs. An independent economic impact analysis has estimated an annual impact of $515 million in St. Louis County. Before the formal permit application process started in April 2016, the NorthMet Project underwent more than a decade of environmental review, culminating in the state’s EIS adequacy decision in March 2016.

There are three main areas of focus of the permit to mine application: mine waste management, wetlands protection and replacement, and financial assurance.

For mine waste management, the application explains how PolyMet would design, manage, and monitor mining, waste rock and tailings facilities throughout active mine operations and closure. It details the robust engineering controls PolyMet developed based on more than ten years of extensive analysis and modeling. These controls include stockpile liners, containment systems, drainage and dust control systems, water treatment facilities and other means for ensuring compliance with state and federal regulations.

For wetlands protection and replacement, the application provides plans to protect wetlands as well as replacement and mitigation for the wetlands the project would directly impact. This includes plans for restoring, maintaining and monitoring wetlands, as well as monitoring all wetlands near the project that could be indirectly affected by operations.

For financial assurance, the application outlines bankruptcy-proof financial assurance that PolyMet would provide to ensure the state can close and reclaim the site even if, for any reason, the company were unable to do so.

State law requires an annually updated contingency reclamation plan and cost estimate that describes closure and post-closure activities that would be necessary if operations were to cease within the next year. The NorthMet Project’s first year of activity is construction, for which the reclamation cost estimate is $12 million. PolyMet also provided projections for the second year of construction and first year of operation, which are $44 million and $197 million, respectively.

The projections reflect progressively greater reclamation cost as the project footprint expands and the need for long-term water treatment becomes necessary for the project.

PolyMet proposes to use a mix of financial assurance instruments comprising surety bonding, irrevocable letters of credit, and a trust fund in accordance with Minnesota Rules. The mix would evolve over time, and would be supplemented by PolyMet with environmental insurance as necessary. In aggregate, the total amount of financial assurance available at any time would equal the estimated cost of the reclamation plan, applicable at that time, in compliance with state law. This would include water treatment.


About PolyMet
PolyMet Mining Corp. is a publicly-traded mine development company that owns 100 percent of Poly Met Mining, Inc., a Minnesota corporation that controls 100 percent of the NorthMet copper-nickel-precious metals ore body through a long-term lease and owns 100 percent of the Erie Plant, a large processing facility located approximately six miles from the ore body in the established mining district of the Mesabi Iron Range in northeastern Minnesota. Poly Met Mining, Inc. has completed its definitive feasibility study. The NorthMet final EIS was published in November 2015, preparing the way for decisions on permit applications. NorthMet is expected to require approximately two million hours of construction labor, creating approximately 360 long-term jobs, a level of activity that will have a significant multiplier effect in the local economy.

To stop by PolyMet’s website, CLICK HERE


Be in-the-know when you’re on-the-go!

FREE eNews delivery service to your email twice-weekly. With a focus on lead-driven news, our news service will help you develop new business contacts on an on-going basis.
CLICK HERE to register your email address.


Copyright © 2016 Mining Connection LLC. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed without permission.

For licensing permission, .(JavaScript must be enabled to view this email address)

Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




Advertisement