Galena Mining Begins $15M Surface Infrastructure Development at Abra Base Metals Project
Galena Mining Ltd has commenced surface infrastructure works at the Abra Base Metals Project in the Gascoyne region of Western Australia.
The company has started this work program prior to finalization of key engineering procurement and construction (EPC) and mining services contracts for the construction of the plant and development of the boxcut/underground mine.
Galena Managing Director Alex Molyneux said: “The construction works now commenced at Abra are significant and most of them form part of what might go into a final EPC package so we’re genuinely getting a ‘jump’ on things to fast-track the overall timetable to production.”
Infrastructure works that have already commenced include the following:
• Site clearing and roadworks – Initial works have focused on topsoil clearing and storage, ground preparation at the permanent camp site and various site and access roadworks.
• Water supply and waste water treatment facility – Equipping the previously drilled and prepared water production bores with pumps and constructing pipelines, together with construction and connection of waste water treatment facilities.
• Permanent camp construction – Deployment to Abra and on-site assembly of the initial 80-person accommodation units of the permanent camp along with the final camp sized kitchen and messing facilities, together with on-site civil works and connection to services.
The above works have been facilitated by the establishment of a 24-person accommodation unit temporary construction camp at the project that will be used to house workers until the permanent camp is ready for habitation by the end of the year.
The commenced surface infrastructure development activities are part of a $15 million development works program.
The work program is being conducted to the scope of the previously announced Abra bankable / definitive feasibility study and they’re significant in that they represent about 9% of the total project pre-development capital expenditure.
Moving forward with such a major infrastructure development program at this time has been made possible by a combination of Galena’s strong availability of equity funds and good progress being made with respect to the project financing debt process.
Source: Proactive Investors
About Galena Mining
The company owns 100 percent of the Abra base metals deposit located in the Gascoyne Region of Western Australia. The Abra deposit was discovered in 1981 and remains one of the biggest undeveloped lead deposit in the World. Abra is within a granted mining lease.
The Galena Mining team has prior experience at bringing an exploration project through all stages of development and into production.
To stop by Galena’s website, CLICK HERE
Be in-the-know when you’re on-the-go!
FREE eNews delivery service to your email twice-weekly. With a focus on lead-driven news, our news service will help you develop new business contacts on an on-going basis.
CLICK HERE to register your email address.