Virginia Regulators Reject Plan to Extend Life of John Amos and Mountaineer Power Plants, W.Va.

Published: August 26, 2021 |

[Click image to enlarge]

The Virginia Corporation Commission on Monday rejected Appalachian Power’s plan to keep the John Amos and Mountaineer power plants in West Virginia operating through 2040.

The commission denied the company permission to make wastewater treatment upgrades at the plants and pass the cost on to electric power customers in the state.

Not making those upgrades would require the plants to close in 2028, under U.S. Environmental Protection Agency rules.

West Virginia’s Public Service Commission earlier this month approved Appalachian Power’s plan for Amos, in Putnam County, and Mountaineer, in Mason County.

It also approved similar upgrades to the Mitchell plant in Marshall County, which is jointly operated by Wheeling Power and Kentucky Power.

West Virginia customers will start to see a slight increase on their bills next month as a result.

Still, the decision by Virginia regulators casts doubt on whether the projects at Amos and Mountaineer will move forward.

Regulators in Kentucky in July rejected Kentucky Power’s portion of the upgrades to Mitchell.

It’s unclear if the wastewater projects at all three plants can be completed with only West Virginia customers paying for the cost.

In a statement, Phil Moye, a spokesman for Appalachian Power, said the company would use the same approach to all three plants.

“Our next steps will be to evaluate our options in light of the conflicting Virginia and West Virginia state commission orders, determine the best path forward to meet the resource needs in each state, and return to the commissions if necessary for consideration of our updated costs and plans,” Moye said.

American Electric Power, which owns all three plants, has set a goal of cutting its carbon dioxide emissions by 80 percent of 2000 levels by 2030. Closing the three West Virginia plants and replacing them with cleaner sources of electricity would help the company achieve that goal.

The company argued in all three states that upgrading the plants was better for ratepayers than finding replacement capacity.

Only West Virginia agreed.

Source: Ohio Valley Resource


About American Electric Power
American Electric Power, based in Columbus, Ohio, is focused on building a smarter energy infrastructure and delivering new technologies and custom energy solutions to customers. AEP’s approximately 16,800 employees operate and maintain the nation’s largest electricity transmission system and more than 223,000 miles of distribution lines to efficiently deliver safe, reliable power to nearly 5.5 million regulated customers in 11 states. AEP also is one of the nation’s largest electricity producers with approximately 30,000 megawatts of diverse generating capacity, including more than 5,500 megawatts of renewable energy. AEP’s family of companies includes utilities AEP Ohio, AEP Texas, Appalachian Power (in Virginia and West Virginia), AEP Appalachian Power (in Tennessee), Indiana Michigan Power, Kentucky Power, Public Service Company of Oklahoma, and Southwestern Electric Power Company (in Arkansas, Louisiana, east Texas and the Texas Panhandle). AEP also owns AEP Energy, AEP Energy Partners, AEP OnSite Partners, and AEP Renewables, which provide innovative competitive energy solutions nationwide.

To stop by AEP’s website, CLICK HERE


Be in-the-know when you’re on-the-go!

FREE eNews delivery service to your email twice-weekly. With a focus on lead-driven news, our news service will help you develop new business contacts on an on-going basis.

CLICK HERE to register your email address.

Advertisement




Advertisement




Advertisement




Advertisement




Advertisement




Advertisement